Production Capacity and Lead Times

 

For events with fixed dates, realistic production scheduling is essential. Our stated capacity is up to 300,000 custom medals and approximately 500 custom trophies per month.

Sampling

15–35 days; around 15 days for existing-mold designs and up to 35 days for new tooling

Medal production

Approximately 18 days for 5,000 pieces; the source says this can include mold making. Larger or more complex orders may need roughly 10 additional days. Timing is recalculated if sample approval is required first.

Trophy production

Approximately 20–45 days, depending on dimensions, complexity, finishing and quantity

International shipping

Quoted separately; indicative air freight 5–7 days, express 5–10 days and sea freight to Europe 30–35 days [VERIFY by route and service]

Rush production

Subject to feasibility: medals from 15 days, trophies from 20 days, with a stated 10% rush surcharge

Lead times exclude international transit unless explicitly stated in the quotation. Final schedules depend on specifications, approvals and production availability. If your event deadline is tight, tell us the required delivery date when requesting a quote.